Penang Hospital’s RM758m development projects progressing as planned, set for completion by 2029, says state exco

5
Penang Hospital’s RM758m development projects progressing as planned, set for completion by 2029, says state exco

AI Summary

Three development projects worth RM758 million at Penang Hospital are progressing as scheduled. The Women and Children's Block (RM307 million) is 34.35% complete and expected to finish by January 2026, featuring a 329-bed, eight-story building and a 12-story car park. The Stem Cell Centre Block (RM23 million) is slated for completion in March 2027 and will enhance transplant services. The largest project, a RM428 million Specialist Clinic and Ward, will include a 14-story building with 216 beds and is expected by May 2029. All projects are funded by the federal government under the 10th and 11th Malaysia Plans.